We are pleased to inform you that construction of the school building is complete. The site was demobilized (construction materials were cleared and the laborers have moved off the location) after completing the external finishing work on the campus. The plaque and signage (according to your specifications) have also been placed at the campus. Furthermore, furniture has been placed and uniforms, books & supplies have been delivered to the school. Number of faculty staff (teachers + principal) and non-faculty staff (Admin Assistant, Driver, Aya, Chawkidar) hired for this campus is 5 & 4 respectively.

Construction of TCF School – OGS Trust Campus has been completed. Classes will commence from the new academic session 2017 starts in April. This is a dual unit primary school.

Project Summary

Academic Year 2015-16
No. of Units Two Primary Units*
Construction Timeline Oct 2015 – Oct 2016
Location Khuda Ki Basti, Surjani Town, Karachi
Total Student Capacity 360 (180/unit)
Operational Year April 2017
Building Status Complete

*Each unit is an academic block, or one section per class. Primary=KG to V

Funds Summary

Description Amounts in PKR
Funds Committed For Establishment 30,000,000
a. Funds Received 30,000,000
b. Funds Remaining 0
Operational Support (2017-20) 8,000,000
c. Funds Received 8,000,000
d. Funds Remaining 0
Total Amount Requested (b + d) 0

Campus Configuration

This campus follows the standard TCF remote model design for a dual unit primary school. It is a purpose-built campus with 10 classrooms (5/unit) from KG to V, each with a capacity of 30 students per class. The school has an administration block which includes principal’s office, an account assistant’s office and a faculty common room. The building also accommodates spacious corridors, a library / art room, a playground and toilets, and is equipped with other essentials such as running water, and electricity.

Construction Work Task List

Layout and Design Complete
Preparation of Tender Document Complete
Award of Contract Complete
Mobilization of Contractor at site Complete
Excavation and foundation Complete
Plinth Complete
Brick/Block masonry Complete
Roof Slab Complete
Interior Plaster (Ceiling & Wall plaster) & Tile Works Complete
Plumbing & Electric Work Complete
Fixing of Doors, Windows, Green Boards, other equipment Complete
Exterior Finishing (external plaster, pointing or cladding & projection plaster) Complete
Grinding & polishing of tiles and paint work Complete
Installation of Signage & Plaque Text Received & Installed
Site Clearance Complete

Project Construction Timeline

Pictures of the Campus

[row] [column col=”6″][/column] [column col=”6″] [/column] [/row]  
[row] [column col=”6″][/column] [column col=”6″] [/column] [/row]

Login required to proceed.

If you don’t have an account as yet then please

  Or